The development of Melbourne Square has been holistically planned to meet and exceed your highest expectations. We are so proud to now be partaking in the exciting milestone of handing you the keys to your new home. For future residents we are looking forward to welcoming your new home at Melbourne Square later this year.

Updates

EAST TOWER:

  • Core being poured to L65
  • L60 slabs complete
  • L61 slab construction underway
  • Façade install commenced L56 typical panels
  • L42-L50 finishes and fit-out in progress
  • Woolworths secondary slab concrete placement and polishing in progress
  • Woolworths fit-out works in progress

WEST TOWER:

  • L54 roof - Damper tank installation complete
  • L41-L53 finishes and fit-out in progress
  • Lifts 1-4 complete
  • External tower facade clean in progress

PODIUM:

  • L8 pool construction in progress

We are open by private appointment only
As per the new regulation, we are practicing safe social distancing guidelines including observing a distance of 1.5m between people, registering your attendance, using hand sanitiser upon entry and limiting 1 household per appointment. Enquire now to book an inspection.

Corner Power & Kavanagh Streets, Southbank, Melbourne, Australia.
Call 1300 888 770 or Register Now


View Display Suite Map
-->