BLVD Construction Update – February 2025

BLVD Construction Update – February 2025

We are excited to share the latest progress on BLVD as construction continues. Below is an overview of the key activities scheduled for the next few months:

  • Completion of bulk earthworks and excavation.
  • Raft slab concrete pour for the building foundations.
  • Tower crane 2 will be installed during this period with all works conducted within the site boundary to minimize disruption to surrounding areas.
  • Deliveries of materials and equipment to site for structural works.
  • Approved Traffic Management Plan to ensure orderly movement of construction vehicles and deliveries, with minimal impact on local traffic.

We remain committed to minimizing disruption to the surrounding community.

  • Noise: Some noise may be associated with concrete pouring and equipment loading, but we will ensure it is minimized and complies with Melbourne City Council guidelines.
  • Pedestrian and Traffic Management: Temporary adjustments to pedestrian paths may occur during construction vehicle movements.

Settlements are due to start from late 2026 with full completion of the building expected in early 2028.

Please keep an eye out for future updates and if you have any questions regarding the BLVD development, please email karen.abbey@oskp.com.au.