MARCH 2020 CONSTRUCTION UPDATE

East Tower:

• Core being poured to L60
• L54 slabs complete
• L55 slab construction in progress
• L55 typical tower screen establishment in progress
• L32-L49 finishes and fit-out in progress
• L48 façade installation complete
• L49-50 in progress

West Tower:

• L53 plant room construction in progress
• L54 roof plant works in progress
• L31-L53 finishes and fit-out in progress
• L54 roof façade installation in progress
• L53 façade installation complete
• Roof façade installation in progress

SETTLEMENT UPDATE

First stage handover for Melbourne Square is currently in progress. We are pleased to advise on the latest settlement rollout structure to welcome our new residents into the project.

Settlement for the second stage is in May/June.


Display Suite and Display Apartments Open Daily by Appointment 10am-5pm
Corner Power & Kavanagh Streets, Southbank, Melbourne, Australia.
Call 1300 888 770 or Register Now


View Display Suite Map