CONSTRUCTION MILESTONES ACHIEVED

East Tower:

• Core being poured to L54
• L49 slabs complete
• L50 slabs in progress
• L45 curtain wall installation in progress.
• L09-L44 finishes and fitout in progress.

West Tower:

• Core pours complete (topped out),
• L53 slabs complete
• L54 slabs in progress
• L49 curtain wall installation in progress
• L09-L48 finishes and fit-out in progress

SETTLEMENT UPDATE

OSK settlement team will be your point of contact for matters relating to your Melbourne Square purchase. We will advise you
of settlement timing, assist you with  nance enquiries, as well
as conduct bank valuations and purchaser inspections. For legal matters you must continue to liaise with your solicitor/conveyancer. If you haven’t already appointed a conveyancer, please do so immediately.

Levels 2—20
Settlements are targeted for mid-January. Notification email from OSK Property’s lawyer, Maddocks is targeted to send out in early January. We will continue with our purchaser inspections and valuations in December through the Christmas shut down period up to Level 20

Levels 21—31
Settlements are targeted for late January. We will start the process from early January 2020. To book in inspections or valuations, please liaise and send booking requests through to settlement team: