Construction is advancing quickly and first settlements are well on track.

 

East Tower:

  • Core 2 works to pour 100mm above L30 SRL in progress
  • L26 in progress
  • L21 curtain wall installation in progress
  • L09-L20 finishes and fitout in progress

West Tower:

  • Core 3 works to pour 100mm above L32 SRL in progress
  • L28 in progress

West Tower:

  • L23 curtain wall installation in progress
  • L09-L22 finishes and fit-out in progress
  • Podium - Fitout and Finishes
  • B1, L00 and L01 fitout and finishes in progress
  • L02, L03, L04, L05, L06 and L07 apartment, back of house and carpark fitout in progress
  • FS-01 facade module installation in progress on both East and West